JSBs per week
By JSB date of completion
This week's compliance
Foremen with a JSB in the last 7 days
3 of 5 active foremen turned in a JSB in the last 7 days
Foreman compliance — last 12 weeks
JSBs per foreman per week (Mon–Sun). Rolling window; not affected by the date filter.
| Foreman / Crew Lead | Aug 17 | Aug 24 | Aug 31 | Sep 7 | Sep 14 | Sep 21 | Sep 28 | Oct 5 | Oct 12 | Oct 19 | Oct 26 | Nov 2 | Total | Last JSB |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Charles Kinard | × | × | × | 1 | × | × | × | 1 | 23d | |||||
| Hunter Dye | × | 1 | 1 | × | × | × | × | 2 | 35d | |||||
| John Hart | × | × | 1 | 3 | 1 | 4 | 1 | 10 | 6d | |||||
| Lance Edwards | × | × | 4 | 7 | 3 | 2 | 4 | 20 | 2d | |||||
| Michael McNeal | 1 | × | × | 2 | 1 | × | 1 | 5 | 1d | |||||
| Weekly total | — | — | — | — | 1 | 1 | 6 | 13 | 5 | 6 | 6 | — | 38 |
JSB quality
How completely crews are filling out the brief
- Job steps listedAt least one task step written in the steps table71% 27/38Watch
- Hazard named for every stepEach listed step has a potential hazard filled in55% 21/38Gap
- Safe action for every stepEach listed step has a recommended safe action47% 18/38Gap
- Emergency plan completeHospital name, hospital address and notification person all filled in95% 36/38On target
- Muster point identifiedMuster point field filled in50% 19/38Gap
- Clearance holder namedOf JSBs with energy isolation checked, how many name who holds the clearance74% 26/35Watch
- JSB index # recordedJSB Index # filled in (needed to tie a JSB to a work order)34% 13/38Gap
- Supervisor / inspector sign-offInspector name filled in26% 10/38Gap
Exposures briefed
Share of JSBs with each control section checked — click a section for the controls
Crews check an average of 7.8 of 9 sections per JSB. When nearly every section is checked on every job, the boxes stop telling you what is different about today's work; the written job steps below carry that signal.
Hazards crews wrote in their job steps
Free-text hazards grouped by category · share of JSBs mentioning each
- Electrical Contact / Energized Lines37% (14)
- Pinch Points / Crushing34% (13)
- Traffic / Work Zone32% (12)
- Struck By / Falling Objects26% (10)
- Vehicle / Driving24% (9)
- Wildlife / Vegetation24% (9)
- Strains / Ergonomic24% (9)
- Pole / Structure Failure18% (7)
- Weather / Environmental18% (7)
- Falls / Slips & Trips18% (7)
- Rigging / Equipment Failure16% (6)
- Cuts / Lacerations16% (6)
Required PPE
Share of JSBs listing each item
- Safety glasses97% (37)
- FR clothing97% (37)
- Work gloves97% (37)
- Hi-vis traffic vest97% (37)
- Hard hat / Class E95% (36)
- 100% fall protection (harness / lanyard / SRL)92% (35)
- Switch stick / hot stick92% (35)
- Tested rubber gloves & sleeves (by class)89% (34)
- Leather protectors89% (34)
- Proper footwear (EH-rated)89% (34)
- Traffic cones & signs89% (34)
- Insulated line tools87% (33)
- Voltage detector71% (27)
- Temporary protective grounds55% (21)
Type of work
- Overhead distribution87% (33)
- Storm restoration18% (7)
- Other3% (1)
- Transmission3% (1)
Permits noted
Share of JSBs
- Hot Work Permit55% (21)
- Excavation Permit32% (12)
- Working at Heights Permit24% (9)
- Electrical Isolation / LOTO Permit24% (9)
- Crane / Lifting Permit16% (6)
- Confined Space Permit13% (5)
FR clothing category
- CAT 295% (36)
- Yes3% (1)
- CAT 43% (1)
Job sites
Road abbreviations combined (CR, Co Rd, County rd → County Road)
- County Road 117014
- 8129 County Road 11803
- Jefferson County2
- County Road 11802
- 11200 County Road 11601
- Cs 25501
- 1019 St Nicholas Ave1
- 1215 S Presley St Atmore Al.1
- 5800 State Line Rd1
- 2951 Cottage Grove Dr1
Crew Member JSB History
Every JSB a person signed onto, as foreman or team member — all dates
Start typing a name to pull up their full JSB history.