American Current

Job Safety Brief

Sat, October 10, 2026
Foreman / Crew Lead
John Hart
Job site
Jefferson county
Type of work
Storm restoration
JSB index #
1

Job details

Job activity
Storm restoration
Weather
Rainey
Crew on site
Ryder, Matt, Alex,Davis, John
Submitted by
ryderhart807@gmail.com

Emergency information

Notification person
Ryder
Backup
Matt
Radios & cell working
Yes
Nearest hospital
UAB medical west hospital
Hospital address
35022, 1201 11th ave S, Birmingham, Al, 35205
Muster point
Forman truck
Injury hotline
CORE 844-953-8234 (24/7) · 911 for emergencies

Job steps, hazards & safe actions

#Job stepPotential hazardsSafe actions
1Drive to job Wet roads, other traffic Use causation when driving , check surrounds before merging lanes and watch other drivers
2Put out signs and cones Getting hit by car Look before entering roadway
3Hanging grounds Generator back feed Test wire before hanging ground
4Remove tree off of line Falling trees, wire breaking or poles breaking Secure wire before cutting tree, stay clear of tree falling
5Remove grounds and re energize wire Energize line Make sure all men and equipment are in the clear, check rest of line before re-energizing
6Drive back Traffic and wet roads Take precaution while driving

Energy isolation

Clearance / control held by
John hart
FR clothing (min.)
CAT 2

Hazard controls briefed

Energized Electrical

  • Voltage identified / treat as energized until proven otherwise
  • Minimum Approach Distance established and briefed
  • Cover-up / rubber goods installed (line hose, blankets, hoods)
  • Rubber gloves and sleeves inspected, air-tested, and in test date
  • Protective grounds / equipotential grounding installed
  • Switching, clearance, or hold card obtained and isolation verified
  • Test before touch
  • Backfeed controlled (customer generators / parallel sources)
  • Step and touch potential controlled

Energy Isolation & Control

  • Clearance / control in place
  • Protective grounds installed

Aerial Lift / Digger Derrick / Crane

  • Equipment inspected
  • Outriggers set and cribbing used
  • Spotter used
  • No personnel under suspended load

Climbing & Fall Protection

  • Harness and lanyard / SRL inspected
  • Anchorage point identified
  • Rescue-at-height plan

Ladders

  • Inspect before use
  • Use 3-point contact
  • Secure ladder at top or bottom

Work Zone & Traffic Control

  • Signs, cones, and flaggers
  • High-visibility clothing

Storm & Environmental

  • Generator backfeed controlled
  • Chainsaw / vegetation

Human Performance

  • Pre-task planning
  • Fit for duty
  • Stop and think
  • Peer check
  • Avoid rushing
  • Verify critical steps
  • Ask questions
  • Job briefing held with all crew (OSHA 1910.269)

Required PPE

Hard hat / Class ESafety glassesFR clothingTested rubber gloves & sleeves (by class)Leather protectorsWork glovesProper footwear (EH-rated)100% fall protection (harness / lanyard / SRL)Temporary protective groundsSwitch stick / hot stickInsulated line toolsHi-vis traffic vestTraffic cones & signs

Crew (5)

4 team member signatures captured · Job briefing acknowledged (OSHA 1910.269)