| # | Job step | Potential hazards | Safe actions |
|---|---|---|---|
| 1 | Removing three pot bank | Not checking voltage and rotation | Check voltage and rotation before and after removing and installing |
| 2 | Moving primary | Entergized primary, improper cover up, bad arm or pole up and down stream | Keep distance between phases, cover up work area properly, check structures up and down stream before moving wire. |
| 3 | Framing and setting poles | Entergized primary, pole coming Entergized, getting in pinch points | Cover primary before setting pole, look up and down the line when moving wire, keep hands and body out of pinch points. |
6 team member signatures captured · Job briefing acknowledged (OSHA 1910.269)